Abstract:Ship block construction process under modern lean shipbuilding mode and
the method of planning shipbuilding in our country are analyzed and
summarized. Combining PERT with CPM, the ship block construction plan is
created, and the building plan is coordinated and optimized in duration
and cost. An applied program using VBA based on MS-Project software is
developed to implement the method. As an instance, the block
construction planning of a tanker in a Dalian shipyard is programmed and
optimized. The calculated instance and results show that the approach is
feasible and practical to make ship block construction plan in the early
days of shipbuilding.