基于PERT与CPM的船舶分段建造计划协调与优化

Hits:

Date of Publication:2011-01-01

Journal:大连理工大学学报

Affiliation of Author(s):运载工程与力学学部

Volume:51

Issue:5

Page Number:681-687

ISSN No.:1000-8608

Abstract:Ship block construction process under modern lean shipbuilding mode and
   the method of planning shipbuilding in our country are analyzed and
   summarized. Combining PERT with CPM, the ship block construction plan is
   created, and the building plan is coordinated and optimized in duration
   and cost. An applied program using VBA based on MS-Project software is
   developed to implement the method. As an instance, the block
   construction planning of a tanker in a Dalian shipyard is programmed and
   optimized. The calculated instance and results show that the approach is
   feasible and practical to make ship block construction plan in the early
   days of shipbuilding.