Indexed by:期刊论文
Date of Publication:2015-04-01
Journal:COMPUTERS AND GEOTECHNICS
Included Journals:SCIE、EI、Scopus
Volume:65
Page Number:87-96
ISSN No.:0266-352X
Key Words:Earth-rockfill dam; Back-analysis; Parallel algorithm; Mutation particle swarm optimization
Abstract:Deformation control is a central problem in earth-rockfill dam design. The finite element method (FEM) is the primary method used to analyze and predict the deformation of earth-rockfill dams. The parameters of the constitutive model of soil used in earth-rockfill dams determine the FEM analysis results. Using prototype monitoring displacements, the soil parameters of the Malutang II concrete face rockfill dam were back-analyzed using parallel mutation particle swarm optimization. The calculated displacements of the back-analyzed soil parameters are consistent with the prototype monitoring results. The parallel mutation particle swarm optimization has a high optimization rate and can be used in large-scale practical engineering applications. The back-analysis results indicate that the deformation moduli of rockfills in the Malutang II are affected by construction situ. (C) 2014 Elsevier Ltd. All rights reserved.