Leading Scientist:Shao Longtan
Project Participants:郭晓霞
Supported by:企事业单位委托科技项目
Status:结题
Supported by:南京梅山发展有限公司矿业分公司
Nature of Project:横向
Date of Project Approval:2012-09-17
Date of Project Initiation:2012-09-17
Scheduled completion time:2013-09-17
Date of Project Completion:2020-06-30
Pre One:南芬选矿厂卧龙沟尾矿库三维渗流模拟试验及防洪系统水工模型试验
Next One:大孤山球团厂尾矿库165m~180m加高扩容工程坝体静、动力稳定性分析研究