Current position: Home - Research Project
伊江上游水电项目密松水电站引水发电建筑物有限元静动力数值分析
Release Time:2019-03-21 Hits:
Leading Scientist:马震岳
Project Participants:杨庆,王刚,张运良,Hongxiang Tang
Project Source:企事业单位委托科技项目
Status:结题
Supported by:Yangtze River Surveying, Planning and Design Research Co., Ltd.
Nature of Project:横向
Date of Project Approval:2011-06-21
Scheduled Completion Time:2011-10-30
Date of Project Initiation:2011-06-21