基于PERT与CPM的船舶分段建造计划协调与优化
点击次数:
发表时间:2011-01-01
发表刊物:大连理工大学学报
所属单位:运载工程与力学学部
卷号:51
期号:5
页面范围:681-687
ISSN号:1000-8608
摘要:Ship block construction process under modern lean shipbuilding mode and
the method of planning shipbuilding in our country are analyzed and
summarized. Combining PERT with CPM, the ship block construction plan is
created, and the building plan is coordinated and optimized in duration
and cost. An applied program using VBA based on MS-Project software is
developed to implement the method. As an instance, the block
construction planning of a tanker in a Dalian shipyard is programmed and
optimized. The calculated instance and results show that the approach is
feasible and practical to make ship block construction plan in the early
days of shipbuilding.