6500HP港作拖轮低温管路应力分析计算及LNG船用燃料罐应力分析计算

Release Time:2019-03-21  Hits:

Leading Scientist: Yan Lin

Project Participants: yuyanyun

Project Source: 企事业单位委托科技项目

Status: 结题

Supported by: Hubei Difeng Ship Technology Co., Ltd.

Nature of Project: 横向

Date of Project Approval: 2014-09-26

Scheduled Completion Time: 2015-09-30

Date of Project Initiation: 2014-05-01

Date of Project Completion: 2020-06-30