Professor
Supervisor of Doctorate Candidates
Supervisor of Master's Candidates
Main positions: President of international exchange committee of the Chinese Society of Rock Mechanics and Engineering CSRME
Other Post: Vice President of the Chinese Society of Rock Mechanics and Engineering CSRME
Title of Paper:岩质边坡微震活动特征及其施工响应分析
Hits:
Date of Publication:2022-06-30
Journal:岩石力学与工程学报
Volume:34
Issue:5
Page Number:968-978
ISSN No.:1000-6915
Abstract:The stability of high rock slope is one of the important issues during
the construction of hydropower station. The stability of the left bank
slope at Jinping I hydropower station was the key issue due to its high
geo-stress,developed faults and fissures,large-scale excavation,deep
unloading and complicated geological conditions. The characteristics of
the microseismic activity of the left bank slope were introduced
firstly. Analyses of the temporal and spatial distributions of the
microseismic activity in the processes of excavation-induced unloading
and under the excavation conditions during the different periods and in
the different regions were conducted. The correlation among the
initiation,propagation,extension and coalescence of micro-fractures of
rock and the rock mass damage were discussed. The correlation between
the microseismic activity and the construction response at the left bank
slope was also obtained. The results showed that the microseismic
activity induced by the unloading relaxation of the deep rock mass as
results of the excavation of the foundation pit of dam,the X shafts for
lamprophyre vein replacement and the drainage tunnels at the elevation
of 1670 m and the consolidation grouting of weak layers inside the rock
slope reflected in real time the construction conditions on site very
well.
Note:新增回溯数据
Open time:..
The Last Update Time: ..